Project Overview
The Moss Vale Road Urban Release project is currently under construction through Shoalhaven Water. This project was constructed to supply adequate future surfacing to the urban release area. On behalf of Hisway as a part of stage 3 in the project, Superior HDD was involved in the HDD and installation of a new rising main connecting the Cambewarra and Bomaderry wastewater network.
Most recently the team at Superior HDD have installed multiple 630mm OD HDPE pipes at various locations as part of the new rising main construction. The rising main was installed in bore holes up to 200 meters in length in hard rock ground conditions. The project proved to be no challenge for Superior HDD with a successful completion of all HDD works.